GATE 2026 MN – Question 42

Mineral Economics, Mine Planning, Systems Engineering · Systems Engineering · 2 marks · Multiple choice

Dumpers arrive exponentially at5/hour and loading times are exponential. Waiting cost is₹200 per dumper-hour. Shovels S1,S2,S3,S4 have operating costs₹800,850,920,1000/hour and loading rates8,9,10,11 dumpers/hour respectively. Ignore hiring cost. Which minimises operating plus queue-waiting cost?

  1. S1
  2. S2
  3. S3
  4. S4

Practise this question in The GATE Grind →

Show answer and explanation

Correct answer: (B) S2

Explanation

For an M/M/1 queue, Lq=λ²/[μ(μ−λ)]. At λ=5 the four queue lengths are1.0417,0.6944,0.5 and0.3788. Add200Lq to each operating cost: approximately1008.33,988.89,1020 and1075.76 rupees/hour. The smallest is S2, B. Waiting here excludes the dumper actually being loaded.